5G SEAGUL
- Corridor: Sofia (Bulgaria) - Kulata/Promahonas - Velestino (Greece)
- Length: 473 km
- Spectrum bands: 700MHz and 3.5Ghz
- Total EU Grant: €5,748,000.00
- Project duration: 36 months (January 2023 - December 2025)
This project, led by WINGS ICT Solutions, Cosmote and A1 Bulgaria EAD, will target the deployment and upgrade of 5G RAN for transportation uses with a focus on connectivity across the border between Bulgaria and Greece to support Connected and Automated Mobility (CAM) services. The project aims to achieve an optimum network interconnection and roaming/handover configuration while measuring the smooth handover experienced by connected vehicles and validating via real-life cross-border trials.
MEDCOR5G
- Corridor: Barcelona – Figueres (Spain)/ Perpignan - Montpellier – Toulouse (France)
- Lenght: 328 km stretch of roadway in France and 220 km in Spain
- Spectrum bands: 700MHz and 3.5Ghz
- Total EU Grant: €5,204,747.96
- Project duration: 36 months
Led by Tradia Telecom in collaboration with Cellnex France, this project aims to establish uninterrupted 5G coverage along the cross-border sections of the Mediterranean corridor, focusing on areas where market investment in passive/active infrastructure is lacking. The goal is to ensure continuous coverage, maintaining a high-quality service to support Connected Automated Mobility (CAM) services. The project involves the construction of new radio sites in regions with limited or no 5G coverage, benefiting various stakeholders, including Mobile Network Operators (MNOs), road/rail infrastructure operators, and Original Equipment Manufacturers (OEMs).
5G Delux
- Corridor: Frisange (Luxembourg) - Aspelt/Altwies - Saarbrucken (Germany)
- Lenght: 98 km
- Spectrum bands: 700 MHz, 900 MHz and 3.6 GHz
- Total EU Grant: €6,338,325.50
- Project duration: 36 months (January 2023 – December 2025)
5G DeLux is a joint effort between Telekom Deutschland, Post Luxembourg and BMW Group that aims to enable high-performing network coverage and a seamless handover of connected devices when crossing the German-Luxembourgish border. This seamless handover solution should be a blueprint solution for intra-EU borders.
5G NETC
- Corridor: Sweden - Finland - Latvia
- Length: > 2000 km
- Spectrum bands: 3GPP TS 38.101-1 V16.12.1 (2022-06): n28 703 MHz – 748 MHz/758 MHz – 803 MHz (FDD); n78 - 3300 MHz – 3800 MHz (TDD)
- Total EU Grant: €15,535,000.00
- Project duration: 36 months (May 2022 – April 2025)
5G NETC aims to improve cross-border network service continuity for established services and adopt 5G infrastructure in public environments to support new 5G services and applications. The project is a joint effort from Telia Sweden, Telia Finland and Latvia Mobilais Telefons. The goal is to enable applications and services for road CAM and Future Railway Mobile Communication Systems (FRMCS) use case solutions and their introduction.
5G Brno – Bratislava
- Corridor: Brno (Czech Republic) - Lanžhot / Kúty – Bratislava (Slovak Republic)
- Length: 141 km
- Spectrum bands: 5G (700MHz, 3.4-3.8MHz, ITS 5.9GHz, 26GHz), FRMCS (900MHz, 1900MHz)
- Total EU Grant: €300,000
- Project duration: 11 months (January 2023 – November 2023)
5G Brno – Bratislava is a study carried out by the Czech Republic (Správa železnic) together with the Slovak Republic (Železnice Slovenskej republiky) to address the implementation of 5G and FRMCS communication systems between Brno and Bratislava. The study aims to prepare for connected and automated mobility services taking into account the existing communication environment and requirements for the transport path.
5G MELUNISA
- Corridor:
- Length:
- Spectrum bands:
- Total EU Grant:
- Project duration:
This inception study, carried out by railway infrastructure managers SNCF Reseau and CFL in a consortium of six partners involving four public Mobile Network Operators (MNOs) from Luxembourg, prepared the deployment of 5G infrastructure for rail use cases. These cover digital railway operation and passenger connectivity enhancement by densifying telecommunications infrastructure and pushing for a complete 5G coverage. To achieve this with optimal resources, cooperation and synergy are key between railway and public mobile network operators.
5G on Track
5GCarolina
21-EU-DIG-5GCarolina: Cross-border Highway 5G Corridor Munich-Prague
5G Carolina is a joint effort from T-Mobile CZ, together with CETIN and Vantage Towers AG as part of a consortium of 13 partners, that aims explicitly at preparing the 5G systems deployment needed along the 5G Corridor Munich-Prague to enable CCAM throughout the network across all Mobile Network Operators and Vehicle Manufacturers.
5G Gail
21-EU-DIG-5G GAIL: Inception study for the deployment of 5G in the cross-border section of the Carnic and Gailtal Alps between Italy and Austria
5G GAIL is a modular study carried out by Cellnex Italia together with OnTower Austria, Autostrade per l’Italia, and the regional Public Authority on the Italian side (Regione Friuli-Venezia Giulia - RFVG) to assess the effort needed to deploy the transport corridor between Italy and Austria across the Tarvis border, with a neutral and agnostic, passive and active, infrastructure dedicated to the development of digital services, and in particular, the deployment of safe, secure, and sustainable high-performance infrastructure, including Gigabit and 5G networks.
5G Estuary
21-EU-DIG-5GE: 5G Estuary
5G Estuary is a study conducted by KPN Netherlands and Orange Belgium to define a cross-border 5G digital corridor for mobility applications and low-altitude aviation that will make essential nodes in the global supply chain more efficient, safer and sustainable.
Latest 5GS
21-EU-DIG-LATEST –5GS: 5G Corridor Study for Latvia, Estonia and Lithuania
The Latest 5GS study, carried out by Tallinn University of Technology (Tallinna Tehnikaülikool - TalTech) together with the Estonian Broadband Association (Eesti Lairiba Arenduse Sihtasutus - ELA SA), Valsts Akciju Sabiedriba Elektroniskie Sakari (VASES), Telia Estonia, and Elisa Estonia, focuses on providing technical solutions and financial model(s) to deploy 5G infrastructure along the Via Baltica and Rail Baltica corridors capable of providing cross-border 5G services in the Baltic States.
EUMOB
21-EU-DIG-EUMOB: Digitisation of European corridors for intelligent mobility
EUMOB is a cross-border feasibility study between Spain and France. The project is a joint effort between Abertis Autopistas Espana, Cellnex France, SANEF, and Tradia Telecom that focuses on the digitalisation of European road infrastructure to support the harmonised deployment of C-ITS services and the subsequent development of service-driven business ecosystems in transport and mobility.
The GUIDE project is a Coordination Support Action funded by the European Union.
Views and opinions expressed are those of the author(s) only and do not necessarily reflect those of the European Union or HADEA. Neither the European Union nor the granting authority can be held responsible for them.